Crooked Creek Area Sewer Improvements Project Update (Belmont North Relief Interceptor) May 16, 2011 CONSTRUCTION UPDATES Section 1: 10th Street/Miley Avenue to 19th Street/Lafayette Road Tentative Schedule: Ongoing through mid-May 2011 Final surface restoration and project clean-up near the 10th Street and Miley Avenue intersection, along Miley Avenue, and along Lafayette Road will be completed mid-May 2011. Section 2: 19th Street/Lafayette Road to 2700 Cold Spring Road Tentative Schedule: Ongoing through mid-May 2011 Permanent pavement striping along Lafayette Road north of 19th Street was completed with the Section 1 project pavement restoration. Final surface restoration and project clean-up will be completed by mid-May 2011. Section 3: 2700 Cold Spring Road to Grandview Drive/Fox Hill Drive Tentative Schedule: Ongoing through December 2011 Merryman
Excavation completed the Septic Tank Elimination Program (STEP) and force main
sewer installation for the entire project area. Temporary pavement has been
installed on Grandview Drive from Kessler Boulevard to Juan Solomon Park and
will be replaced with final pavement in spring 2011. Final pavement is expected
to be complete by June 1. Some construction excavation will occur along
Grandview Drive and at the south side of the intersection of Grandview Drive and
Kessler Boulevard in May so that repairs to the force main sewer and testing can
be completed. Valve installation and repairs to temporary pavement will continue
through May. Section 4: Juan Solomon Park lift station and Coffin Golf Course flow transition building Tentative Schedule: Ongoing through October 2011 FA Wilhelm Construction Company continues dewatering operations to lower the groundwater level as part of the lift station construction at Juan Solomon Park. The contractor has completed pouring the concrete walls and leak testing at the lift station. Additionally, the contractor has completed forming and pouring the diversion structure walls along with foundation footings and walls along the north and east sides of the lift station. Mechanical, electrical, and plumbing work is ongoing inside and outside the lift station. The Juan Solomon Park tennis courts are closed, but public parking is available. Mass excavation for construction of the flow transition building at Coffin Golf Course is complete, and concrete for the base slab, building and stairway walls has been poured. The contractor has completed installation of the 42-inch diameter force main sewer pipe north of the flow transition building and the 48-inch gravity sewer pipe to the south. Also, the contractor installed mechanical equipment inside of the flow transition building and will pour the concrete slab for the maintenance building once the oil/water separator arrives. Lastly, the stone veneer, or decorative building material made to look like natural stone, is being installed at the flow transition building. To receive this project update via e-mail, sign up at www.indy.gov/CrookedCreekSewer. To ensure proper delivery of this message please be sure to add “@indy.gov” to your safe sender list and make sure this address is white-listed by your IT department. Indianapolis Department of Public Works 1200 Madison Ave. Suite 200 |